Cooling has been a supporting role in data centers for decades-air cooling plus fans, air conditioning if not enough. But when the power consumption curve of AI chips almost stands up, the old method completely fails.In 2026, liquid cooling is no longer a multiple choice question, but a red line for survival.

The laws of physics are merciless: power consumption has exceeded the limit of air cooling

Let's look at some hard numbers:

chip/platformpower dissipationcooling solution
Nvidia H100/H200700WAir cooling is feasible
NVIDIA GB2001200WLiquid cooling + air cooling hybrid (cold plate cover chip, storage/IO retention air cooling)
NvidiaGB300(Blackwell Ultra)1400W (top with 1600W)Fully liquid cooled (all devices cooled)
Nvidia Rubin (VR200/VR300)1800W / 2700W100% full liquid cooling,fanless design
Google TPU v7 (Ironwood)980WForced 100% liquid cooling
physical limit of air cooling(Vertiv data)Chip TDP 1000W, stand-alone rack 80kWMore than that, no cooling.

The rack level jump is more intuitive:

A very real consequence:If liquid cooling is not used, the GB300's computing power performance will shrink by at least 40% due to overheating protection.That is to say, the card you bought at a high price can only run out of 60% performance in an air-cooled environment — this is not a question of "do you want liquid cooling", it is "buy a new card must be liquid cooling".

data center Room
Traditional IDC stand-alone rack 2-10kW, AI rack 120kW Start: power density difference of an order of magnitude, cooling mode must be replaced

Permeability data: 2026 is the first year of scale landing

caliber2024202520262027+
Global AI Data Center Liquid Cooling Penetration Rate (TrendForce)14%33%40%——
China market penetration——20%37%More than half of 2027, 82% in 2030
New AIDC liquid cooling ratio (IDC/Gartner combined)Less than 15%——more than 45% of——
Liquid cooling penetration rate of newly built AIDC in China (forecast by brokers)————Breakthrough 80%——

The caliber of different institutions varies greatly (whether the statistical scope is "all data centers" or "new intelligent computing centers"), but the direction is completely the same:From minority to majority in two or three years.

Several measures of market size:

Two technical routes: cold plate is the mainstream, immersion attack limit

dimensionalityCold Plate Liquid CoolingLiquid immersion
theoryCold plate directly attached to CPU/GPU, liquid circulation in the board microchannel to take away heat; storage, IO and other components to retain air coolingImmerse the whole machine in non-conductive coolant, and the whole component will contact the liquid for cooling.
market sharesMainstream, accounting for more than 90% in 2026(The proportion of cold plate in new data center exceeds 80%)25-30%(another caliber), focusing on ultra-high density
advantageHighest maturity, friendly to retrofitting existing air-cooled rooms, good supply chain compatibilityBest cooling efficiency, PUE lower than 1.1, no fan noise, no local hot spots
applicable scenarios1000-1400W class single chip (GB300), 100kW class rackHigh-density scenarios with power density of more than 30kW per unit rack, future 200kW-1MW level
cost structureCold plate 32%+ Quick connector 28%+ CDU 25%=85% of core componentsAbout 10% for pipeline valves; only 5% for coolantHigh coolant ratio (electronic fluorinated fluid or synthetic oil), high tank and sealing requirements
technical thresholdCold plate micro-channel micron processing (five-axis CNC+ vacuum brazing), fast joint tens of thousands of plug and unplug, CDU high reliability 7×24 operationCoolant chemical stability and insulation, sealing system (sealing failure accounts for 60% of total liquid cooling failure)

An easily overlooked reliability statistic:Sealing failures account for 60% of total failures in liquid cooling systems, is the most important reliability risk. The high purity of the coolant and the complex temperature change environment have extremely high requirements for the chemical compatibility and life of the sealing material. The material system has developed from ordinary rubber to fluororubber and even perfluororubber (which can work stably over a wide temperature range from-45℃ to 300℃). This is why liquid cooling is not as simple as "pouring water into the server".

Rack Maintenance
Liquid cooling rack load-bearing increased by 30-50% compared with air cooling: rack, floor load-bearing, pipeline support should be re-calculated

PUE policy tightening: the second driver of liquid cooling

PUE (Power Usage Effectiveness)= Total data center energy consumption divided IT equipment energy consumption, the closer to 1 the better.Cooling systems consume 20%-30% of the total data center energyThis is a key factor affecting PUE.

policy calls for...index
Special Action Plan for Green and Low Carbon Development of Data CenterBy the end of 2025, the national average PUE will drop below 1.5; the PUE of new large-scale projects will be strictly controlled1.25 within; Hub node items are not higher than1.2The proportion of green electricity in the newly built data center of the national hub node exceeds 80%
domestic situationThe average PUE of eight hub node clusters is about 1.3, and the lowest PUE of the most advanced data center is reduced to 1.3.1.04
us/EUNew data center PUE ≤1.2
codes of practiceGlobal Computing Consortium (GCC)"AIDC Infrastructure Scale": Power density of new AIDC single rack ≥50kW,synchronous forced equipped liquid cooling system
March 2026 Four Ministries DocumentMinistry of Industry and Information Technology, National Development and Reform Commission, State-owned Assets Supervision and Administration Commission and National Energy Administration jointly issued, clearly promoting liquid cooling servers and strengthening R & D and application of phase change liquid cooling technology

In other words:Air cooling exit is not only a technical issue, but also a compliance issue.The new AIDC wants to get the index, think about energy efficiency review, liquid cooling is standard.

Industrial Chain and Supply Pattern (Procurement Perspective)

Three evolving directions for technology

  1. The coolant turns green.Environmental regulations impose strict limits on PFAS (Permanent Chemicals) and the global market will accelerate its transition to synthetic oil or bio-based coolants in 2026. Pay attention to environmental compliance of coolants when purchasing and may face replacement requirements in the future.
  2. and waste heat recovery.The 40 - 60 ℃ hot water brought by liquid cooling system is connected to urban heating system in Europe and northern China, and the data center is transformed from "large energy consumer" to "energy station". This is limited in Guangzhou (no heating demand), but it is a return item that can be counted as investment return for northern projects.
  3. Standardization of interfaces.The standardization of liquid cooling interface jointly promoted by OCP (Open Computing Project) and China ODCC has made significant progress in 2026, and CDU and cold plate of different brands begin to realize preliminary exchange. This means that in the future, it is not necessary to be bound by a single manufacturer, and the purchasing bargaining power is enhanced.

Practical impact on SMEs and self-built server rooms

Most SMBs won't buy the GB300 themselves, but the liquid-cooling trend will affect you in three ways:

1. IDC Hosting Price and Availability

The hosting unit price of liquid-cooled racks is higher than that of air-cooled racks (infrastructure investment is larger), but if you want to run high-power AI cards, air-cooled racks simply cannot fit — now many IDC start charging power surcharges for requests for single racks exceeding 8- 10kW, and directly request liquid-cooled racks for more than 20kW or refuse.Clarify your single-rack power requirements before hostingThis is the first sentence of selection.

2. Ceiling of self-built small server room

A typical enterprise self-built equipment room (2-4 racks, precision air conditioning, UPS) can support a single rack power is usually 5-8kW. This means:

equipmentPower consumption per unitFeasibility of self-built server room
1U/2U Universal Server300-600WTotally feasible, a 42 U rack installed 15 - 20 sets about 6 - 10 kW
4-card GPU inference server (RTX 4090 class)2.5-3.5kWIt is feasible, but only 2-3 units can be placed in one rack. It is necessary to confirm the refrigeration margin.
8 card GPU training server (A100/H20 class)5-8kWCritical, requires a single rack refrigeration capacity of 10kW+, most old server rooms do not support
GB 200/GB 300 NVL 72 Rack120-150kWcompletely unworkable, must be liquid cooling room or managed

Practical advice:Reasoning servers with less than 4 cards can be built by themselves (provided that the cooling and power supply of the server room have been evaluated), and those with more than 8 cards are better hosted with a licensed IDC provider.The hidden costs of self-construction (power expansion, precision air conditioning, UPS, fire protection, 7×24 duty, spare parts) usually exceed the cost of colocation in three years.

3. Ask for cooling requirements when purchasing equipment

After 2026 to buy GPU servers, specifications on the "cooling requirements" must be checked one by one: single rack power density, air inlet temperature requirements, whether the need for liquid cooling interface, rack load (liquid cooling rack load than air cooling increased by 30-50%).

Our judgment: who should be cooled now?

ACCPC provides server room construction and services: Data-center planning design (including power density and refrigeration calculation), Structured Cabling, UPS and power distribution, precision air conditioner selection, airflow organization optimization (closed hot and cold channels), rack and equipment shelving, environmental CCTV system, IDC server room hosting coordination (we engage a licensed IDC provider: two-way mains + UPS + diesel + 7×24 duty; air-cooled and liquid-cooled rack options can be assessed). It also conducts server wholesale in Guangzhou and installation and commissioning of server room equipment.&If your server room is worried about cooling, we can do a free power and cooling calculation first.--Give a report on "how many units can be installed now and how many more can be installed with additional equipment", which is cheaper than blindly buying equipment. Telephone020-39029800.